Project Detail

The project, the 2nd phase of which was completed in the Tobolsk Region of Russia, was commissioned in 2019 and is a chemical power plant that has become one of the most prestigious industrial projects in Russia with a capacity of 1.5 million tons. In the project, the construction of which started in May 2015, 676 tons of heavy load lifting operations were carried out.

Employer : ZapSibNeftekhim / LINDE

Contractor : Renaissance Heavy Industries

Sector : Petrochemicals

Location : Tobolsk, Russia

Project Duration: 2017 – 2020

Project Status: Completed

Work Done:

    • Above Ground Pipe Installation – 83,500 WDI
    • Painting Works- A/G Pipelines & Support- 170,000 m2
    • Hydrotesting & Renovation Activities for related works – 650 packs
    • Indirect (24 ppl) & Direct (390 ppl) Management for Related Jobs

Türkiye

 Address:  Barbaros Mah. Mor Menekşe Sok. Teknik Yapı Deluxia Suites No: 3/A D: 207 Ataşehir - İstanbul / TÜRKİYE

  Phone: +7 (911) 338-39-29

  E-mail: info@siriusyapi.com.tr

Rusya

 Address: 115407, Moscow, Intraterritory Municipality Nagatinsky Zaton, Nagatinskaya Embankment, Building 54, Premises 2Ц Moskova/Rusya

 E-mail: info@siriuscons.com

Sirius © 2024 All rights reserved.